Next phase for development of historic Tipperary building


The project will see the building be transformed into a fully accessible business centre
Tipperary County Council have published the plans for the next phase of the Cahir Market House Centre, including for alterations, conservation, and restoration works for the Market House Building and for No 25 Old Church Street. The demolition of the rear part of No 25 is also planned.
A new two-storey extension to the back of No 25 is planned, with new windows, doors, and works to the archway.
The estimate for the contract is €2.4 million, and the ultimate intention of the project is to convert the Market House to a business centre.
Documents from the council indicate that there are no plans to have staff employed for the business centre, but that it could accommodate up to 110 people at any one time, including visitors. They have recently advertised for a contractor to begin the works.
A primary requirement of the council is that the building be accessible at all points, and constructed ‘to allow for independent circulation by people with a wide range of abilities’. Other elements planned are a ‘hearing enhancement system’,
A report on the condition of the timber within the existing building found that ‘significant repair’ is due on the stairs, with steel supports, but the joists on the first floor are in a ‘reasonable condition’.
However, other parts of the building were ‘saturated’ and rotting, with heavy decay suspected in the linings of the courtroom.


The roof is considered to be in a reasonable condition, as is the clocktower despite the ‘generally poor’ detail of some plastic and plywood replacement works in the last 30 years.
The rear roof was also found to be in passable condition, but dry rot found in the first floor room that is shared with No 25.
The Market House dates from about 1770, and in later life until about 1985 was a hardware store and a car showroom. Following that, it was reborn as the courthouse and library; the courthouse is gone, but the library continues. A conservation report lamented the fact that few internal features remain, but nevertheless there is enough documentation and photographs existing so that the outer facade of the building could be restored to its original appearance.
The project is part of the Cahir Town Regeneration Plan, for which €11.9 million was allocated in 2022 by the Department of Rural Development.
The old Granary Building on Church Street will also be refurbished and renovated to become a new Town Library and Gallery.