Latteragh road closure possible but 'end is in sight' for major north Tipperary road project

The Latteragh Realignment Programmeplaceholder image
The Latteragh Realignment Programme | courtesy of Gary Keville Traffic Management Limited

The long-running but necessary roadworks project between Nenagh and Thurles is in the final stretch, as council officials told a meeting on Monday this week how the ‘end is in sight’ for the Latteragh realignment programme

The council have said there’s an ‘end in sight’ for the works at Latteragh between Thurles and Nenagh, as an end date for the extensive road realignment scheme is predicted before the end of June next year.

The works, although necessary, have been an ordeal for many motorists in the last few months.

The Council did not confirm whether a full road closure would be needed and that it was still under discussion; the Council had previously advertised their intention to close the road for two weeks in November between Ballinamona Cross and Borrisoleigh.

The major €30 million project is transforming one of north Tipperary’s most notoriously difficult stretches of road.

In August this year four bridge beams, each weighing 66 tonnes, were successfully installed across the Nenagh River.