2027 for Slievenamon Road improvements in Tipperary

Artist’s impression of what the improvements could look likeplaceholder image
Artist’s impression of what the improvements could look like | Tipperary County Council

The scheme, which will widen footpaths on about half a kilometre of the road, was approved in 2022

The council says that Phase 2 of the N62 Slievenamon Road project, which extends from the roundabout at the shopping centre up to Liberty Square, will be ready for construction in 2027.

The scheme, which involves about half a kilometre of road and is mostly focused on pedestrian and road safety, was given the go-ahead and went through the public consultation process in 2022.

At the time, costs were estimated to be about €3 million. Since then, “complications” with Transport Infrastructure Ireland (TII) funding and an Uisce Éireann Surface Water separation scheme have delayed the project, and in the meantime the Thurles MD has carried out emergency inlay works. However, funding was allocated by the TII earlier this year and consultants for the detailed design (who were appointed in April 2024) have begun their work.

A report with the planning application notes how the area is a “high collision location” and that there are “deficiencies with respect to the road layout, signage and road markings [which]...increase the risk of collisions with pedestrians and vehicles”.

The work is predicted to take 14 months, where the road will be made about 6.5 metres wide, and footpaths to be anything between 1.8 metres and 2.5 metres.

About 11 parking spaces will be provided on the northbound carriageway between Liberty Square and Thomond/ Fianna Road junction.

Another 12 parking spaces will be created at the southern end of the project near to Kavanagh Place. Additionally, there will be a number of formalised parking spaces provided along the southbound carriageway between Thomond/Fianna Road junction and the Thurles Shopping Centre roundabout.

Existing car parking spaces reserved for Thurles Garda Station will stay where they are, and raised table pedestrian crossings will be provided at the Thomond Road and Kavanagh Place junctions.

Drainage works will also be carried out, and public lighting improved.

The next stage of the project is the completion of the ground investigation, and the detailed design and procurement of a works contractor, subject to TII approval.

It is anticipated that the scheme will be ready for construction in 2027.